Georgia Federal Judge: Developer Is Not Entitled To Amend Years After Deadline

(March 20, 2024, 8:41 AM EDT) -- ATLANTA — A developer that originally filed claims for indemnity against a subcontractor for allegedly defective construction work more than nine years ago is not entitled to leave to amend its complaint in light of a Georgia Supreme Court ruling because allowing amendment at this stage would cause undue delay and prejudice to the subcontractor, a Georgia federal judge found in denying the developer’s motion for leave to amend....