Builder Appeals Order Finding Claims Against Dissolved Contractor Were Time-Barred

(January 23, 2024, 8:42 AM EST) -- RENO, Nev. — A builder that allegedly failed to properly construct a large distribution center has appealed to the Ninth Circuit U.S. Court of Appeals a Nevada federal court order finding that its cross-claims for indemnification and contribution against a subcontractor that worked on the project are time-barred by statute because the subcontractor itself was dissolved more than three years before the claims against it were filed....