Georgia Federal Jury Finds Surety Not Responsible For Damages To Army Base

Mealey's (October 29, 2018, 10:16 AM EDT) -- COLUMBUS, Ga. — While a general contractor and a subcontractor were both found responsible for damages arising out of delays to the construction on new barracks at a U.S. Army base, a Georgia federal jury on Oct. 26 found that a surety owed no coverage for the damages (Cleveland Construction Inc. v. Stellar Group Inc., et al., No. 16-179, M.D. Ga.)....