Judge:  Completion Of Home’s Construction Not A Condition For Payment

Mealey's (February 12, 2020, 1:06 PM EST) -- CHICAGO — A federal judge in Illinois on Feb. 10 awarded summary judgment to a seller of manufactured homes accused of construction and structural defects, finding that a man breached the terms of the construction agreement by failing to pay for the building because a certificate of completion was not a precedent to payment under the contract (Christopher Stoller v. CMH Manufacturing West Inc., No. 18 C 0047, N.D. Ill., 2020 U.S. Dist. LEXIS 22334)....