Georgia Federal Judge: Army Corps Unreasonably Delayed Water Allocation Request

Mealey's (October 11, 2017, 8:52 AM EDT) -- ATLANTA — A Georgia federal judge on Sept. 29 said that the U.S. Army Corps of Engineers unreasonably delayed responding to a request by Georgia, the Atlanta Regional Commission and the Cobb-Marietta Water Authority for more water from a reservoir but that the Corps did not fail to update reallocations in its dam control manuals or claims made under the National Environmental Protection Act (NEPA) (State of Georgia, et al. v. The United States Army Corps of Engineers, et al., No. 14-3593, N.D. Ga., Atlanta Div.)....